Thai Solar PV Permit Complianceใบอนุญาตและการปฏิบัติตามกฎระเบียบสำหรับโซลาร์ PV ในประเทศไทย

A practical guide to permits, exemptions and approvals for grid-connected solar PV projects in Thailand.คู่มือเชิงปฏิบัติเกี่ยวกับใบอนุญาต ข้อยกเว้น และการอนุมัติสำหรับโครงการโซลาร์ PV ที่เชื่อมต่อระบบไฟฟ้าในประเทศไทย

  • Research baseline 7 November 2026
  • 15 sections
  • 27 sources

The Thai version of this guide is not available yet. The English text is shown.

An IDN69 Permit Knowledge Hub resource
Know the requirements. Prepare with confidence.

Planning solar PV for a factory, hotel, office, warehouse or other facility? The requirements depend on more than the number of panels. System capacity, installation type, connection arrangement, electricity ownership and site conditions all influence the approvals you need.

This guide brings those requirements together so you can identify the relevant permits, understand available exemptions, prepare supporting documents and plan submissions at the right project phase.

Start with your project size, then check the sections relevant to your installation and location. A licence exemption does not remove every other notification, utility approval or site obligation.

Using this guide: This is a national planning baseline. Exact forms, receiving offices and site-specific conditions should be confirmed against current authority documents before submission. Source numbers such as [R1] correspond to the reference register at the bottom of this page. Preliminary planning allowances are distinguished from official requirements.

แหล่งข้อมูลจาก IDN69 Permit Knowledge Hub
รู้ข้อกำหนด เตรียมตัวอย่างมั่นใจ

กำลังวางแผนติดตั้งโซลาร์ PV ให้โรงงาน โรงแรม สำนักงาน คลังสินค้า หรืออาคารอื่น ๆ ใช่หรือไม่? ข้อกำหนดที่เกี่ยวข้องไม่ได้ขึ้นอยู่กับจำนวนแผงเพียงอย่างเดียว กำลังการผลิตของระบบ ประเภทการติดตั้ง รูปแบบการเชื่อมต่อ ความเป็นเจ้าของไฟฟ้า และสภาพพื้นที่ติดตั้ง ล้วนมีผลต่อใบอนุญาตและการอนุมัติที่ต้องดำเนินการ

คู่มือนี้รวบรวมข้อกำหนดเหล่านั้นไว้ในที่เดียว เพื่อให้คุณระบุใบอนุญาตที่เกี่ยวข้อง ทำความเข้าใจข้อยกเว้นที่มีอยู่ เตรียมเอกสารประกอบ และวางแผนการยื่นเอกสารให้ตรงกับช่วงของโครงการ

เริ่มจากขนาดโครงการของคุณ แล้วตรวจสอบหัวข้อที่เกี่ยวข้องกับการติดตั้งและที่ตั้งของคุณ การได้รับยกเว้นใบอนุญาตไม่ได้ยกเว้นการแจ้ง การขออนุมัติจากการไฟฟ้า หรือภาระหน้าที่ของพื้นที่ติดตั้งอื่น ๆ ทั้งหมด

วิธีใช้คู่มือนี้: นี่คือแนวทางพื้นฐานระดับประเทศสำหรับการวางแผน แบบฟอร์ม หน่วยงานที่รับเรื่อง และเงื่อนไขเฉพาะของแต่ละพื้นที่ ควรตรวจสอบกับเอกสารฉบับล่าสุดของหน่วยงานที่เกี่ยวข้องก่อนยื่นจริง หมายเลขอ้างอิง เช่น [R1] ตรงกับทะเบียนอ้างอิงท้ายหน้านี้ ระยะเวลาและค่าเผื่อสำหรับการวางแผนเบื้องต้นแยกไว้ต่างหากจากข้อกำหนดอย่างเป็นทางการ

Identify your projectระบุลักษณะโครงการของคุณ

This guide covers grid-connected rooftop, solar carport/canopy, ground-mounted and floating PV; owner-funded self-consumption; onsite private PPA or leasing arrangements; electricity export under an eligible utility procurement scheme; and projects in industrial estates. Additional guidance addresses extensions and PV systems with battery storage.

Off-grid installations follow different exemption and connection rules. Transmission-connected developments require a project-specific assessment beyond the ordinary C&I distribution pathway described here.

Start by recording the following project details:

Classification field Required information
Location/network Province, coordinates, actual serving utility or licensed network operator, connection voltage
Installation Existing rooftop, new carport/canopy, ground-mounted, floating or mixed
Commercial arrangement Own-use, onsite PPA, lease, utility sale or supply to other premises
Capacity Panel DC kWp; inverter AC kW and rated kVA; existing and proposed generation separately
System boundary Common busbars, meters, transformers, interconnected buildings, emergency generation and BESS
Land/building Ownership, roof/land lease, meter-holder identity, existing building/factory permissions
Special setting IEAT estate, private industrial park, waterbody, restricted land, public crossings or airport vicinity
Development status New installation, extension, equipment change, ownership transfer or operating-mode change

How to classify your project: The relevant energy thresholds use the applicable generating-source capacity in kVA. Record panel kWp and inverter kVA separately. Export limiting does not by itself establish a lower installed rating for permitting, and separate roofs do not automatically establish separate generating sources. [R1–R3]

คู่มือนี้ครอบคลุมระบบ PV แบบเชื่อมต่อกับระบบไฟฟ้า ทั้งบนหลังคา โรงจอดรถ/หลังคาคลุมโซลาร์ ติดตั้งบนพื้นดิน และแบบลอยน้ำ การลงทุนเองเพื่อใช้ไฟฟ้าเอง การทำสัญญาซื้อขายไฟฟ้า (PPA) หรือเช่าระบบในพื้นที่เอกชน การขายไฟฟ้าตามโครงการรับซื้อไฟฟ้าของการไฟฟ้าที่เข้าเกณฑ์ และโครงการในนิคมอุตสาหกรรม นอกจากนี้ยังมีแนวทางเพิ่มเติมสำหรับการขยายระบบและระบบ PV ที่มีระบบกักเก็บพลังงานแบตเตอรี่

ระบบที่ไม่เชื่อมต่อกับระบบไฟฟ้า (off-grid) ใช้กฎการยกเว้นและการเชื่อมต่อที่แตกต่างออกไป ส่วนโครงการที่เชื่อมต่อกับระบบส่งไฟฟ้าต้องประเมินเป็นรายโครงการ ซึ่งอยู่นอกเหนือขั้นตอนระบบจำหน่ายสำหรับภาคพาณิชย์และอุตสาหกรรม (C&I) ทั่วไปที่อธิบายไว้ในคู่มือนี้

เริ่มต้นด้วยการบันทึกรายละเอียดโครงการดังต่อไปนี้

หัวข้อการจัดประเภท ข้อมูลที่ต้องระบุ
ที่ตั้ง/โครงข่าย จังหวัด พิกัด การไฟฟ้าหรือผู้ให้บริการโครงข่ายที่ได้รับอนุญาตซึ่งให้บริการจริง และระดับแรงดันที่เชื่อมต่อ
การติดตั้ง หลังคาที่มีอยู่เดิม โรงจอดรถ/หลังคาคลุมใหม่ ติดตั้งบนพื้นดิน ลอยน้ำ หรือแบบผสม
รูปแบบเชิงพาณิชย์ ใช้เอง PPA ในพื้นที่ เช่าระบบ ขายให้การไฟฟ้า หรือจ่ายไฟให้สถานที่อื่น
กำลังการผลิต กำลังแผง DC (kWp) กำลังอินเวอร์เตอร์ AC (kW) และพิกัด kVA แยกกำลังการผลิตที่มีอยู่เดิมและที่เสนอใหม่
ขอบเขตของระบบ บัสบาร์ร่วม มิเตอร์ หม้อแปลง อาคารที่เชื่อมต่อถึงกัน เครื่องกำเนิดไฟฟ้าฉุกเฉิน และ BESS
ที่ดิน/อาคาร กรรมสิทธิ์ สัญญาเช่าหลังคา/ที่ดิน ผู้ถือมิเตอร์ และใบอนุญาตอาคาร/โรงงานที่มีอยู่
พื้นที่พิเศษ นิคมอุตสาหกรรมของ กนอ. สวนอุตสาหกรรมเอกชน แหล่งน้ำ พื้นที่หวงห้าม จุดตัดทางสาธารณะ หรือบริเวณใกล้สนามบิน
สถานะการพัฒนา ติดตั้งใหม่ ขยายระบบ เปลี่ยนอุปกรณ์ โอนความเป็นเจ้าของ หรือเปลี่ยนรูปแบบการดำเนินงาน

วิธีจัดประเภทโครงการของคุณ: เกณฑ์กำลังการผลิตด้านพลังงานที่เกี่ยวข้องใช้กำลังของแหล่งผลิตไฟฟ้าที่เกี่ยวข้องในหน่วย kVA ให้บันทึก kWp ของแผงและ kVA ของอินเวอร์เตอร์แยกกัน การจำกัดการส่งออกไฟฟ้าไม่ได้ทำให้พิกัดการติดตั้งที่ใช้ในการขออนุญาตลดลงโดยอัตโนมัติ และหลังคาที่แยกกันก็ไม่ได้ถือเป็นแหล่งผลิตไฟฟ้าแยกกันโดยอัตโนมัติ [R1–R3]

Requirements by project sizeข้อกำหนดตามขนาดโครงการ

The three bands below make the requirements easier to compare. They are IDN69 guidance categories, not official government project names.

Requirement Band S: below 200 kVA Band M: 200 to below 1,000 kVA Band L: 1,000 kVA and above
ERC generation licence Generally exempt; applicable notification remains Generally exempt; applicable notification remains Generally required, subject to any specific legal exemption
Controlled-energy production licence, พค.2 Generally not required Required Required under the applicable licensing route
Utility connection/design approval Required for grid-parallel operation Required Required; study scope depends on network characteristics
Utility inspection/permission to parallel Required Required Required
Building permission Determined by loading, structural works and new structures Same assessment Same assessment
Rooftop solar factory classification Rooftop solar excluded from solar factory classification Same exclusion Same exclusion
Ground/floating factory requirements Separate assessment Separate assessment Separate assessment
Sale/distribution permissions Commercial/network arrangement and exemption assessment Same assessment Same assessment
Environmental documentation Relevant project-category requirements Relevant project-category requirements Applicable CoP, consultation and licence requirements
Estate and special-site permissions Location/work dependent Location/work dependent Location/work dependent

Boundary rules: Exactly 200 kVA enters Band M; exactly 1,000 kVA enters Band L. “Below 200 kW” should not replace “below 200 kVA” without confirming equipment ratings. Use the applicable 2025 ERC notification procedure; older separate exemption-letter workflows may no longer describe the correct sequence. [R1–R3]

Smaller projects generally have fewer energy-permitting steps, but a small ground-mounted, floating or third-party-supply project can have more site-specific obligations than a straightforward rooftop project of greater capacity.

การแบ่งเป็นสามช่วงด้านล่างช่วยให้เปรียบเทียบข้อกำหนดได้ง่ายขึ้น ช่วงเหล่านี้เป็นหมวดหมู่เชิงแนวทางของ IDN69 ไม่ใช่ชื่อประเภทโครงการอย่างเป็นทางการของหน่วยงานรัฐ

ข้อกำหนด ช่วง S: ต่ำกว่า 200 kVA ช่วง M: ตั้งแต่ 200 ถึงต่ำกว่า 1,000 kVA ช่วง L: ตั้งแต่ 1,000 kVA ขึ้นไป
ใบอนุญาตผลิตไฟฟ้าของ กกพ. โดยทั่วไปได้รับยกเว้น แต่ยังต้องแจ้งตามที่เกี่ยวข้อง โดยทั่วไปได้รับยกเว้น แต่ยังต้องแจ้งตามที่เกี่ยวข้อง โดยทั่วไปต้องมี เว้นแต่เข้าข้อยกเว้นทางกฎหมายเฉพาะ
ใบอนุญาตผลิตพลังงานควบคุม พค.2 โดยทั่วไปไม่ต้องมี ต้องมี ต้องมีตามช่องทางการอนุญาตที่เกี่ยวข้อง
การอนุมัติการเชื่อมต่อ/แบบจากการไฟฟ้า ต้องมีสำหรับการเดินเครื่องขนานกับระบบ ต้องมี ต้องมี ขอบเขตการศึกษาขึ้นอยู่กับลักษณะของโครงข่าย
การตรวจสอบ/อนุญาตให้ขนานระบบจากการไฟฟ้า ต้องมี ต้องมี ต้องมี
การอนุญาตด้านอาคาร พิจารณาจากน้ำหนักบรรทุก งานโครงสร้าง และสิ่งปลูกสร้างใหม่ ประเมินเช่นเดียวกัน ประเมินเช่นเดียวกัน
การจัดประเภทโรงงานโซลาร์บนหลังคา โซลาร์บนหลังคาไม่นับเป็นโรงงานโซลาร์ ข้อยกเว้นเดียวกัน ข้อยกเว้นเดียวกัน
ข้อกำหนดโรงงานแบบติดตั้งบนพื้นดิน/ลอยน้ำ ประเมินแยกต่างหาก ประเมินแยกต่างหาก ประเมินแยกต่างหาก
การอนุญาตขาย/จำหน่ายไฟฟ้า ประเมินรูปแบบเชิงพาณิชย์/โครงข่ายและข้อยกเว้น ประเมินเช่นเดียวกัน ประเมินเช่นเดียวกัน
เอกสารด้านสิ่งแวดล้อม ข้อกำหนดตามประเภทโครงการที่เกี่ยวข้อง ข้อกำหนดตามประเภทโครงการที่เกี่ยวข้อง CoP การรับฟังความคิดเห็น และข้อกำหนดใบอนุญาตที่เกี่ยวข้อง
การอนุญาตของนิคมและพื้นที่พิเศษ ขึ้นอยู่กับที่ตั้ง/งานที่ทำ ขึ้นอยู่กับที่ตั้ง/งานที่ทำ ขึ้นอยู่กับที่ตั้ง/งานที่ทำ

กฎเรื่องเส้นแบ่ง: กำลังเท่ากับ 200 kVA พอดีอยู่ในช่วง M และเท่ากับ 1,000 kVA พอดีอยู่ในช่วง L ไม่ควรใช้ “ต่ำกว่า 200 kW” แทน “ต่ำกว่า 200 kVA” โดยไม่ยืนยันพิกัดของอุปกรณ์ก่อน ให้ใช้ขั้นตอนตามประกาศ กกพ. ปี 2568 (2025) ที่ใช้อยู่ในปัจจุบัน ขั้นตอนเดิมที่แยกหนังสือยกเว้นออกต่างหากอาจไม่ตรงกับลำดับที่ถูกต้องอีกต่อไป [R1–R3]

โครงการขนาดเล็กโดยทั่วไปมีขั้นตอนขออนุญาตด้านพลังงานน้อยกว่า แต่โครงการขนาดเล็กที่ติดตั้งบนพื้นดิน ลอยน้ำ หรือจ่ายไฟให้บุคคลที่สาม อาจมีภาระเฉพาะพื้นที่มากกว่าโครงการบนหลังคาทั่วไปที่มีกำลังการผลิตสูงกว่า

Energy licences and exemptionsใบอนุญาตด้านพลังงานและข้อยกเว้น

3.1 Generation-licence exemption notification

Applicability: Generally grid-connected generating sources below 1,000 kVA. The statutory generation-licence exemption and the applicable notification procedure are separate concepts.

Documents: Applicant/authorization information, location, system classification and capacity, electrical design and the utility/network information required by the current route; พค.2 evidence where applicable.

Agency: ERC, coordinated with the utility where the current procedure provides for that arrangement.

Prerequisite: Confirm whether connection is to MEA/PEA or a private network. The relevant 2025 procedure determines how utility submissions and ERC notification are coordinated; a separate ERC letter is not automatically the first step for every project.

Phase/timing: Initiate alongside design and connection submissions; record final notification evidence according to the applicable sequence. The notification timetable depends on the applicable route and its coordination with the utility. [R1, R2]

3.2 Electricity-generation licence

Applicability: Generally grid-connected generation from 1,000 kVA upward, for own-use as well as sale, unless a specific exemption applies.

Documents: Corporate and ownership information; project and financial readiness; site rights; technical design; environmental material; and applicable associated permissions.

Agency: ERC. Relevant section-48 coordination must be identified for associated approvals.

Prerequisite: Determine the generating-source boundary and environmental route early. Treat the licence as a pre-construction development requirement where applicable, not merely a handover document.

Planning allowance: 3–6 months or longer for complex projects. This is an IDN69 preliminary scheduling allowance, not an official service commitment. [R3, R4]

3.3 Controlled-energy production licence — พค.2

Applicability: Generally 200 kVA and above. พค.1 is the application; พค.2 is the licence.

Documents: Applicant/authorization records; engineer-certified layout and SLD; equipment ratings; inspection documentation and readiness notice; site and supply evidence; applicable contractual and environmental attachments.

Agency: ERC, with DEDE technical consideration under the applicable route.

Prerequisite: Follow the current inspection/readiness conditions. A generation-licence exemption does not waive พค.2 in Band M.

Planning allowance: 2–3 months following a complete, inspection-ready submission; verify the current route-specific official period. Prepare the file during construction and complete the required permission before operation.

Document control: The referenced ERC checklist is marked May 2026 and distinguishes new applications, renewals and changes. Select the attachments relevant to your application and check for a newer version before submitting. [R5, R6]

3.4 Electricity sale and distribution

Screen sale licensing separately from generation, and distribution licensing separately from both. An onsite PPA does not automatically mean a separately licensed sale or distribution business; relevant exemptions and point-of-use interpretations must be assessed.

Prepare the customer PPA, network diagram, supply points, capacity, land/cable rights and commercial/operator information. ERC is the principal classification authority. Resolve the route before making unconditional commercial commitments.

Planning allowance: 2–4 months if a licensed route applies; classification and exemption assessment may follow a different timetable. [R3, R4]

3.5 Commencement of licensed operations

For applicable licensed projects, maintain a separate commencement-notification task. Use the current solar checklist and rooftop self-declaration route where applicable, together with completion and compliance evidence.

The general published guidance requires advance notice of at least 15 days, but the project file must verify the currently applicable procedure and licence conditions. This task is distinct from notification of exempt generation. [R7, R8]

3.1 การแจ้งเพื่อรับยกเว้นใบอนุญาตผลิตไฟฟ้า

ขอบเขตการใช้: โดยทั่วไปใช้กับแหล่งผลิตไฟฟ้าที่เชื่อมต่อกับระบบไฟฟ้าและมีกำลังต่ำกว่า 1,000 kVA การยกเว้นใบอนุญาตผลิตไฟฟ้าตามกฎหมายกับขั้นตอนการแจ้งที่เกี่ยวข้องเป็นคนละเรื่องกัน

เอกสาร: ข้อมูลผู้ยื่น/การมอบอำนาจ ที่ตั้ง การจัดประเภทและกำลังของระบบ แบบทางไฟฟ้า และข้อมูลการไฟฟ้า/โครงข่ายที่ช่องทางปัจจุบันกำหนด พร้อมหลักฐาน พค.2 ในกรณีที่เกี่ยวข้อง

หน่วยงาน: กกพ. โดยประสานกับการไฟฟ้าในกรณีที่ขั้นตอนปัจจุบันกำหนดให้ประสานงาน

เงื่อนไขเบื้องต้น: ยืนยันว่าเชื่อมต่อกับ กฟน./กฟภ. หรือโครงข่ายของเอกชน ขั้นตอนปี 2568 (2025) ที่เกี่ยวข้องเป็นตัวกำหนดวิธีประสานการยื่นต่อการไฟฟ้ากับการแจ้ง กกพ. การส่งหนังสือแจ้ง กกพ. แยกต่างหากไม่ใช่ขั้นตอนแรกของทุกโครงการโดยอัตโนมัติ

ช่วงเวลา/ระยะเวลา: เริ่มดำเนินการควบคู่ไปกับการออกแบบและการยื่นขอเชื่อมต่อ และบันทึกหลักฐานการแจ้งขั้นสุดท้ายตามลำดับขั้นตอนที่เกี่ยวข้อง ระยะเวลาการแจ้งขึ้นอยู่กับช่องทางที่เกี่ยวข้องและการประสานกับการไฟฟ้า [R1, R2]

3.2 ใบอนุญาตผลิตไฟฟ้า

ขอบเขตการใช้: โดยทั่วไปใช้กับการผลิตไฟฟ้าที่เชื่อมต่อกับระบบไฟฟ้าตั้งแต่ 1,000 kVA ขึ้นไป ไม่ว่าจะใช้เองหรือขาย เว้นแต่เข้าข้อยกเว้นเฉพาะ

เอกสาร: ข้อมูลนิติบุคคลและความเป็นเจ้าของ ความพร้อมด้านโครงการและการเงิน สิทธิในพื้นที่ แบบทางเทคนิค เอกสารด้านสิ่งแวดล้อม และใบอนุญาตที่เกี่ยวข้อง

หน่วยงาน: กกพ. ต้องระบุการประสานงานตามมาตรา 48 ที่เกี่ยวข้องสำหรับการอนุมัติที่เกี่ยวเนื่อง

เงื่อนไขเบื้องต้น: กำหนดขอบเขตของแหล่งผลิตไฟฟ้าและช่องทางด้านสิ่งแวดล้อมตั้งแต่ต้น ให้ถือว่าใบอนุญาตเป็นข้อกำหนดของการพัฒนาโครงการที่ต้องมีก่อนก่อสร้างในกรณีที่เกี่ยวข้อง ไม่ใช่เพียงเอกสารที่ส่งมอบตอนท้าย

ค่าเผื่อสำหรับการวางแผน: 3–6 เดือน หรือนานกว่านั้นสำหรับโครงการที่ซับซ้อน นี่คือค่าเผื่อกำหนดการเบื้องต้นของ IDN69 ไม่ใช่คำมั่นของหน่วยงานในการให้บริการ [R3, R4]

3.3 ใบอนุญาตผลิตพลังงานควบคุม — พค.2

ขอบเขตการใช้: โดยทั่วไปใช้กับระบบตั้งแต่ 200 kVA ขึ้นไป พค.1 คือใบคำขอ พค.2 คือใบอนุญาต

เอกสาร: บันทึกผู้ยื่น/การมอบอำนาจ แผนผังและแผนผังระบบไฟฟ้าเส้นเดี่ยว (SLD) ที่วิศวกรรับรอง พิกัดอุปกรณ์ เอกสารการตรวจสอบและหนังสือแจ้งความพร้อม หลักฐานพื้นที่และการจ่ายไฟ และเอกสารแนบด้านสัญญาและสิ่งแวดล้อมที่เกี่ยวข้อง

หน่วยงาน: กกพ. โดย พพ. (DEDE) พิจารณาด้านเทคนิคตามช่องทางที่เกี่ยวข้อง

เงื่อนไขเบื้องต้น: ปฏิบัติตามเงื่อนไขการตรวจสอบ/ความพร้อมในปัจจุบัน การได้รับยกเว้นใบอนุญาตผลิตไฟฟ้าไม่ได้ยกเว้น พค.2 ในช่วง M

ค่าเผื่อสำหรับการวางแผน: 2–3 เดือนหลังยื่นเอกสารครบถ้วนและพร้อมรับการตรวจสอบ ควรตรวจสอบระยะเวลาอย่างเป็นทางการของช่องทางที่ใช้อยู่ในปัจจุบัน เตรียมแฟ้มเอกสารระหว่างก่อสร้าง และให้ได้รับอนุญาตที่จำเป็นก่อนเริ่มเดินเครื่อง

การควบคุมเอกสาร: รายการตรวจเอกสารของ กกพ. ที่อ้างถึงลงวันที่เดือนพฤษภาคม 2569 (May 2026) และแยกคำขอใหม่ การต่ออายุ และการเปลี่ยนแปลงออกจากกัน ให้เลือกเอกสารแนบที่เกี่ยวข้องกับคำขอของคุณ และตรวจสอบว่ามีฉบับใหม่กว่าก่อนยื่น [R5, R6]

3.4 การขายและการจำหน่ายไฟฟ้า

ให้พิจารณาใบอนุญาตขายไฟฟ้าแยกจากการผลิต และใบอนุญาตจำหน่ายไฟฟ้าแยกจากทั้งสองอย่าง PPA ในพื้นที่ไม่ได้หมายความว่าเป็นธุรกิจขายหรือจำหน่ายไฟฟ้าที่ต้องมีใบอนุญาตแยกต่างหากโดยอัตโนมัติ ต้องประเมินข้อยกเว้นที่เกี่ยวข้องและการตีความเรื่องจุดใช้ไฟฟ้า

เตรียม PPA กับลูกค้า แผนผังโครงข่าย จุดจ่ายไฟ กำลังการผลิต สิทธิในที่ดิน/สายเคเบิล และข้อมูลเชิงพาณิชย์/ผู้ดำเนินการ กกพ. เป็นหน่วยงานหลักในการจัดประเภท ควรยืนยันช่องทางให้ชัดเจนก่อนให้คำมั่นเชิงพาณิชย์แบบไม่มีเงื่อนไข

ค่าเผื่อสำหรับการวางแผน: 2–4 เดือน หากเข้าช่องทางที่ต้องมีใบอนุญาต การประเมินการจัดประเภทและข้อยกเว้นอาจใช้ระยะเวลาต่างออกไป [R3, R4]

3.5 การเริ่มดำเนินการตามใบอนุญาต

สำหรับโครงการที่ต้องมีใบอนุญาต ให้กำหนดงานแจ้งการเริ่มดำเนินการแยกต่างหาก ใช้รายการตรวจสำหรับโซลาร์ฉบับปัจจุบันและช่องทางการรับรองตนเองสำหรับโซลาร์บนหลังคาในกรณีที่เกี่ยวข้อง พร้อมหลักฐานการก่อสร้างแล้วเสร็จและการปฏิบัติตามข้อกำหนด

แนวทางที่เผยแพร่ทั่วไปกำหนดให้แจ้งล่วงหน้าอย่างน้อย 15 วัน แต่แฟ้มโครงการต้องตรวจสอบขั้นตอนและเงื่อนไขใบอนุญาตที่ใช้อยู่ในปัจจุบัน งานนี้แยกจากการแจ้งการผลิตไฟฟ้าที่ได้รับยกเว้น [R7, R8]

Grid connection, metering and electricity exportการเชื่อมต่อระบบไฟฟ้า การวัดหน่วย และการส่งออกไฟฟ้า

Approval/task Applicability and documents Prerequisite Phase and planning allowance
Connection/design approval and parallel-operation agreement Every grid-parallel PV installation, including zero-export. Meter-holder authority, bill/meter data, site plan, certified SLD, inverter/protection evidence and proposed metering/export controls Utility acceptance of capacity, equipment, protection and connection arrangement Feasibility/design; allow 1–3 months for ordinary C&I distribution cases
Connection study/reinforcement Where the network operator requires impact studies, transformer/switchgear work, telemetry or other reinforcement Defined connection point, voltage, installed/export rating and operating modes Before design commitment; additional months may be necessary
Inspection and authorization to parallel Approved/as-built design, engineer certificates, commissioning/protection results, applicable permits, agreement and payments Conditions satisfied and defects closed Commissioning; allow 2–6 weeks after readiness, excluding reinforcement
Utility procurement acceptance/PPA Electricity sold to utility for payment; scheme application, eligibility, site rights, proposal, security and prescribed permits An available procurement scheme and accepted application; grid approval alone does not create sale entitlement Development through COD; scheme-specific, often several months or longer

Apply the requirements of your actual network operator. MEA and PEA may have different equipment, protection and metering requirements. Power-quality metering and transformer-related limits should be checked against that operator’s current rules. EGAT and private-network connections require separate assessment. [R9–R12]

Residential electricity-purchase programmes are not automatically available to C&I customers. Offsite private PPA/wheeling arrangements require explicit confirmation of an available legal and network-access route.

การอนุมัติ/งานที่ต้องทำ ขอบเขตการใช้และเอกสาร เงื่อนไขเบื้องต้น ช่วงเวลาและค่าเผื่อสำหรับการวางแผน
การอนุมัติการเชื่อมต่อ/แบบ และข้อตกลงการเดินเครื่องขนานระบบ ทุกการติดตั้ง PV ที่เดินเครื่องขนานกับระบบไฟฟ้า รวมถึงแบบไม่ส่งออกไฟฟ้า (zero-export) เอกสารได้แก่ หนังสือมอบอำนาจจากผู้ถือมิเตอร์ ข้อมูลใบแจ้งหนี้/มิเตอร์ แผนผังพื้นที่ SLD ที่วิศวกรรับรอง หลักฐานอินเวอร์เตอร์/ระบบป้องกัน และการควบคุมมิเตอร์/การส่งออกที่เสนอ การไฟฟ้ายอมรับกำลังการผลิต อุปกรณ์ ระบบป้องกัน และรูปแบบการเชื่อมต่อ ช่วงศึกษาความเป็นไปได้/ออกแบบ เผื่อเวลา 1–3 เดือนสำหรับกรณีระบบจำหน่าย C&I ทั่วไป
การศึกษาการเชื่อมต่อ/การเสริมระบบ ในกรณีที่ผู้ให้บริการโครงข่ายกำหนดให้ศึกษาผลกระทบ ปรับปรุงหม้อแปลง/สวิตช์เกียร์ ติดตั้งระบบโทรมาตร หรือเสริมระบบอื่น ๆ กำหนดจุดเชื่อมต่อ แรงดัน พิกัดที่ติดตั้ง/ส่งออก และรูปแบบการเดินเครื่องให้ชัดเจน ก่อนผูกพันการออกแบบ อาจต้องใช้เวลาเพิ่มอีกหลายเดือน
การตรวจสอบและการอนุญาตให้ขนานระบบ แบบที่ได้รับอนุมัติ/แบบตามที่ก่อสร้างจริง ใบรับรองวิศวกร ผลการทดสอบการเดินเครื่อง/ระบบป้องกัน ใบอนุญาตที่เกี่ยวข้อง ข้อตกลง และการชำระเงิน เป็นไปตามเงื่อนไขครบถ้วนและปิดข้อบกพร่องแล้ว ช่วงทดสอบเดินเครื่อง เผื่อเวลา 2–6 สัปดาห์หลังพร้อมตรวจ ไม่รวมงานเสริมระบบ
การรับซื้อไฟฟ้าโดยการไฟฟ้า/PPA ไฟฟ้าที่ขายให้การไฟฟ้าเพื่อรับค่าตอบแทน ใบสมัครโครงการ คุณสมบัติ สิทธิในพื้นที่ ข้อเสนอ หลักประกัน และใบอนุญาตที่กำหนด ต้องมีโครงการรับซื้อไฟฟ้าที่เปิดรับ และใบสมัครได้รับการยอมรับ การอนุมัติการเชื่อมต่อเพียงอย่างเดียวไม่ทำให้เกิดสิทธิขายไฟฟ้า ตั้งแต่พัฒนาโครงการจนถึง COD ขึ้นอยู่กับโครงการ มักใช้เวลาหลายเดือนหรือนานกว่านั้น

ให้ปฏิบัติตามข้อกำหนดของผู้ให้บริการโครงข่ายที่ให้บริการคุณจริง กฟน. และ กฟภ. อาจมีข้อกำหนดด้านอุปกรณ์ ระบบป้องกัน และมิเตอร์ที่ต่างกัน ควรตรวจสอบมิเตอร์วัดคุณภาพไฟฟ้าและข้อจำกัดที่เกี่ยวกับหม้อแปลงกับกฎปัจจุบันของผู้ให้บริการรายนั้น การเชื่อมต่อกับ กฟผ. และโครงข่ายเอกชนต้องประเมินแยกต่างหาก [R9–R12]

โครงการรับซื้อไฟฟ้าสำหรับที่อยู่อาศัยไม่ได้เปิดให้ลูกค้า C&I โดยอัตโนมัติ ส่วน PPA เอกชนนอกพื้นที่/การใช้โครงข่ายร่วม (wheeling) ต้องยืนยันให้ชัดเจนว่ามีช่องทางทางกฎหมายและการเข้าถึงโครงข่ายรองรับ

Building, rooftop and structural requirementsข้อกำหนดด้านอาคาร หลังคา และโครงสร้าง

Current baseline: Ministerial Regulation No. 72, B.E. 2568, published 19 November 2025, replaces the former solar-rooftop provision. Rooftop solar installations with total weight not exceeding 20 kg/m² in any particular area are classified as not constituting building alteration. The former residential-only 160 m² test is no longer the current general rooftop rule. [R13]

Situation Required action / exemption Supporting material / authority Phase and allowance
Qualifying installation on an existing roof Record the applicable non-alteration basis; อ.1 is not automatically required for qualifying installation work Loading/layout evidence; local authority clarification if scope is uncertain Design; an exempt activity has no separate permit-processing allowance
Loading above the exemption, or separate regulated structural alteration Assess อ.1 or an available statutory notification route Owner/title documents, existing permission, drawings, calculations, professional and supervision documents; competent building authority Before relevant works; 1–3 months preliminary allowance
New solar carport/canopy, equipment room or support structure Screen new construction independently from panel loading Architectural/structural/foundation design, site rights and required professional certifications Before construction; project-specific
Required completion/use authorization for associated buildings Screen based on building type, approved work and applicable building legislation Completion certifications, inspection records and prescribed forms Completion before controlled use where applicable

IDN69 engineering standard: Retain roof-condition, localized loading, wind-uplift and attachment assessments even where the permit exemption applies. These IDN69 engineering controls support safe design; they are distinct from the statutory conditions of the rooftop non-alteration exemption.

เกณฑ์พื้นฐานปัจจุบัน: กฎกระทรวง ฉบับที่ 72 พ.ศ. 2568 ประกาศเมื่อวันที่ 19 พฤศจิกายน 2568 (19 November 2025) ใช้แทนบทบัญญัติเดิมเรื่องโซลาร์บนหลังคา การติดตั้งโซลาร์บนหลังคาที่มีน้ำหนักรวมไม่เกิน 20 กก./ตร.ม. ในพื้นที่ใด ๆ ถือว่าไม่เป็นการดัดแปลงอาคาร เกณฑ์เดิมที่ใช้เฉพาะที่อยู่อาศัยและกำหนดพื้นที่ 160 ตร.ม. ไม่ใช่กฎทั่วไปสำหรับโซลาร์บนหลังคาในปัจจุบันอีกต่อไป [R13]

สถานการณ์ การดำเนินการที่ต้องทำ / ข้อยกเว้น เอกสารประกอบ / หน่วยงาน ช่วงเวลาและค่าเผื่อ
การติดตั้งที่เข้าเกณฑ์บนหลังคาที่มีอยู่เดิม บันทึกหลักเกณฑ์ที่ใช้ว่าไม่เป็นการดัดแปลง ไม่จำเป็นต้องยื่น อ.1 โดยอัตโนมัติสำหรับงานติดตั้งที่เข้าเกณฑ์ หลักฐานน้ำหนักบรรทุก/แผนผัง สอบถามหน่วยงานท้องถิ่นหากขอบเขตงานไม่ชัดเจน ช่วงออกแบบ กิจกรรมที่ได้รับยกเว้นไม่มีค่าเผื่อสำหรับการดำเนินการขออนุญาตแยกต่างหาก
น้ำหนักบรรทุกเกินเกณฑ์ยกเว้น หรือมีงานดัดแปลงโครงสร้างที่อยู่ในการควบคุมแยกต่างหาก ประเมิน อ.1 หรือช่องทางการแจ้งตามกฎหมายที่มีอยู่ เอกสารสิทธิ์/ผู้เป็นเจ้าของ ใบอนุญาตเดิม แบบ รายการคำนวณ เอกสารผู้ประกอบวิชาชีพและผู้ควบคุมงาน หน่วยงานควบคุมอาคารที่มีอำนาจ ก่อนเริ่มงานที่เกี่ยวข้อง ค่าเผื่อเบื้องต้น 1–3 เดือน
โรงจอดรถ/หลังคาคลุมโซลาร์ ห้องอุปกรณ์ หรือโครงสร้างรองรับใหม่ พิจารณาการก่อสร้างใหม่แยกจากน้ำหนักบรรทุกของแผง แบบสถาปัตยกรรม/โครงสร้าง/ฐานราก สิทธิในพื้นที่ และใบรับรองของผู้ประกอบวิชาชีพที่กำหนด ก่อนก่อสร้าง ขึ้นอยู่กับโครงการ
การอนุญาตให้ใช้/เสร็จสิ้นการก่อสร้างสำหรับอาคารที่เกี่ยวเนื่อง พิจารณาตามประเภทอาคาร งานที่ได้รับอนุญาต และกฎหมายควบคุมอาคารที่เกี่ยวข้อง ใบรับรองการก่อสร้างเสร็จ บันทึกการตรวจสอบ และแบบฟอร์มที่กำหนด ให้เสร็จสิ้นก่อนใช้งานในส่วนที่อยู่ในการควบคุม ในกรณีที่เกี่ยวข้อง

มาตรฐานวิศวกรรมของ IDN69: ควรเก็บการประเมินสภาพหลังคา น้ำหนักบรรทุกเฉพาะจุด แรงยกจากลม และการยึดติด แม้ว่าจะเข้าข้อยกเว้นการขออนุญาตแล้วก็ตาม มาตรการทางวิศวกรรมของ IDN69 เหล่านี้ช่วยให้การออกแบบปลอดภัย และแยกต่างหากจากเงื่อนไขตามกฎหมายของข้อยกเว้นการไม่ดัดแปลงอาคารสำหรับโซลาร์บนหลังคา

Factory and industrial-estate requirementsข้อกำหนดด้านโรงงานและนิคมอุตสาหกรรม

6.1 Factory legislation

The amended factory regime excludes rooftop solar at all capacities from the solar factory-licensing classification. Rooftop capacity above 1 MW therefore does not, by itself, trigger a solar factory licence. [R14]

For ground-mounted/floating PV, review factory classification, the existing host factory's scope and any expansion/change requirements separately. The competent route may involve DIW, the Provincial Industry Office, ERC section-48 coordination or IEAT, depending on the project.

Documents: Existing factory permissions, land rights, site/machinery layout, generation schedule, safety/environmental information and proposed change details.

Phase/timing: Development before regulated installation/change; 2–4 months preliminary allowance if a permission is required. Existing host-factory electrical safety obligations remain a separate compliance topic. [R3, R15]

6.2 IEAT industrial estates

Screen land-use/business permission, amendments, construction permission and commencement requirements separately. Rooftop factory exclusion alone does not establish exemption from every estate obligation.

Documents: Existing IEAT permissions, roof/land rights and consents, operator/project details, layout and electrical/environmental information.

Agency: IEAT and the relevant estate office. A privately operated industrial park is not automatically an IEAT estate.

Planning allowance: 1–2 months for an ordinary permission/amendment assessment, subject to the actual service category. Complete relevant approvals before construction or activity change. [R16, R17]

6.1 กฎหมายโรงงาน

ระบบกฎหมายโรงงานที่แก้ไขแล้วไม่นับโซลาร์บนหลังคาทุกขนาดกำลังเป็นการจัดประเภทโรงงานโซลาร์ที่ต้องมีใบอนุญาต ดังนั้นโซลาร์บนหลังคาที่มีกำลังเกิน 1 MW ไม่ได้ทำให้ต้องขอใบอนุญาตโรงงานโซลาร์เพียงเพราะเหตุนั้น [R14]

สำหรับ PV แบบติดตั้งบนพื้นดิน/ลอยน้ำ ให้ตรวจสอบการจัดประเภทโรงงาน ขอบเขตของโรงงานเดิมที่เป็นเจ้าของพื้นที่ และข้อกำหนดการขยาย/เปลี่ยนแปลงแยกต่างหาก ช่องทางที่มีอำนาจอาจเกี่ยวข้องกับ กรอ. สำนักงานอุตสาหกรรมจังหวัด การประสานงานตามมาตรา 48 ของ กกพ. หรือ กนอ. แล้วแต่โครงการ

เอกสาร: ใบอนุญาตโรงงานที่มีอยู่ สิทธิในที่ดิน แผนผังพื้นที่/เครื่องจักร กำหนดการผลิตไฟฟ้า ข้อมูลความปลอดภัย/สิ่งแวดล้อม และรายละเอียดการเปลี่ยนแปลงที่เสนอ

ช่วงเวลา/ระยะเวลา: พัฒนาโครงการก่อนการติดตั้ง/เปลี่ยนแปลงที่อยู่ในการควบคุม ค่าเผื่อเบื้องต้น 2–4 เดือนหากต้องขออนุญาต ภาระด้านความปลอดภัยทางไฟฟ้าของโรงงานเดิมที่เป็นเจ้าของพื้นที่ยังคงเป็นเรื่องการปฏิบัติตามข้อกำหนดแยกต่างหาก [R3, R15]

6.2 นิคมอุตสาหกรรมของ กนอ.

พิจารณาการอนุญาตการใช้ที่ดิน/การประกอบกิจการ การแก้ไข การอนุญาตก่อสร้าง และข้อกำหนดการเริ่มดำเนินการแยกต่างหาก การที่โซลาร์บนหลังคาไม่นับเป็นโรงงานไม่ได้หมายความว่าได้รับยกเว้นภาระทุกอย่างของนิคม

เอกสาร: ใบอนุญาต กนอ. ที่มีอยู่ สิทธิและหนังสือยินยอมเรื่องหลังคา/ที่ดิน รายละเอียดผู้ดำเนินการ/โครงการ แผนผัง และข้อมูลด้านไฟฟ้า/สิ่งแวดล้อม

หน่วยงาน: กนอ. และสำนักงานนิคมที่เกี่ยวข้อง สวนอุตสาหกรรมที่ดำเนินการโดยเอกชนไม่ใช่นิคมของ กนอ. โดยอัตโนมัติ

ค่าเผื่อสำหรับการวางแผน: 1–2 เดือนสำหรับการพิจารณาการอนุญาต/การแก้ไขโดยทั่วไป ขึ้นอยู่กับประเภทบริการจริง ให้ได้รับการอนุมัติที่เกี่ยวข้องครบถ้วนก่อนก่อสร้างหรือเปลี่ยนแปลงกิจกรรม [R16, R17]

Environmental requirements and public participationข้อกำหนดด้านสิ่งแวดล้อมและการมีส่วนร่วมของประชาชน

Topic Application principle Preparation and timing
ERC CoP/report/checklist Select the current category for rooftop, ground-mounted or floating PV and the project's licence status; do not label CoP a universal standalone permit Project description, environmental measures, consultation where required, monitoring and decommissioning measures; integrate with licensing
Public participation Apply the applicable ERC process and project-category rules; capacity alone is not a complete decision rule Identify stakeholders, notices, consultation records and issue responses early
EIA/IEE Screen sensitive location, associated regulated works and host-project approvals separately Existing EIA/conditions, change description and required studies; obtain the competent authority's determination
Ongoing compliance Record environmental conditions and reporting obligations Monitoring calendar, responsibilities and evidence during construction/operation

Do not apply a thermal-power 10 MW EIA threshold automatically to solar PV. A project may require CoP compliance without EIA; a sensitive site or alteration to an approved host development may introduce a separate environmental approval route. [R18–R20]

Planning allowances: CoP/consultation 2–4 months or longer; full environmental assessment, where actually triggered, 6–12+ months. These are budgeting/scheduling assumptions, not statutory processing promises.

หัวข้อ หลักการใช้ การเตรียมการและช่วงเวลา
CoP/รายงาน/รายการตรวจของ กกพ. เลือกประเภทปัจจุบันสำหรับ PV บนหลังคา ติดตั้งบนพื้นดิน หรือลอยน้ำ และตามสถานะใบอนุญาตของโครงการ อย่าเรียก CoP ว่าเป็นใบอนุญาตแยกที่ใช้กับทุกกรณี รายละเอียดโครงการ มาตรการด้านสิ่งแวดล้อม การรับฟังความคิดเห็นในกรณีที่กำหนด มาตรการติดตามตรวจสอบและการรื้อถอน ให้บูรณาการเข้ากับการขอใบอนุญาต
การมีส่วนร่วมของประชาชน ใช้กระบวนการของ กกพ. ที่เกี่ยวข้องและกฎตามประเภทโครงการ กำลังการผลิตเพียงอย่างเดียวไม่ใช่กฎตัดสินที่สมบูรณ์ ระบุผู้มีส่วนได้ส่วนเสีย ประกาศ บันทึกการรับฟังความคิดเห็น และการตอบข้อกังวลตั้งแต่เนิ่น ๆ
EIA/IEE พิจารณาพื้นที่อ่อนไหว งานที่อยู่ในการควบคุมที่เกี่ยวเนื่อง และการอนุมัติของโครงการหลักแยกต่างหาก EIA/เงื่อนไขที่มีอยู่ รายละเอียดการเปลี่ยนแปลง และการศึกษาที่จำเป็น ขอความเห็นของหน่วยงานที่มีอำนาจ
การปฏิบัติตามข้อกำหนดอย่างต่อเนื่อง บันทึกเงื่อนไขด้านสิ่งแวดล้อมและภาระการรายงาน ปฏิทินการติดตามตรวจสอบ ผู้รับผิดชอบ และหลักฐานระหว่างก่อสร้าง/เดินเครื่อง

อย่านำเกณฑ์ EIA ของโรงไฟฟ้าพลังความร้อนที่ 10 MW มาใช้กับโซลาร์ PV โดยอัตโนมัติ โครงการอาจต้องปฏิบัติตาม CoP โดยไม่ต้องทำ EIA ส่วนพื้นที่อ่อนไหวหรือการเปลี่ยนแปลงโครงการหลักที่ได้รับอนุมัติแล้ว อาจทำให้มีช่องทางการอนุมัติด้านสิ่งแวดล้อมแยกต่างหาก [R18–R20]

ค่าเผื่อสำหรับการวางแผน: CoP/การรับฟังความคิดเห็น 2–4 เดือนหรือนานกว่านั้น การประเมินผลกระทบสิ่งแวดล้อมเต็มรูปแบบในกรณีที่เข้าเกณฑ์จริง 6–12 เดือนขึ้นไป ตัวเลขเหล่านี้เป็นสมมติฐานสำหรับจัดทำงบประมาณ/กำหนดการ ไม่ใช่คำมั่นเรื่องระยะเวลาดำเนินการตามกฎหมาย

Land use, floating solar and special locationsการใช้ที่ดิน โซลาร์ลอยน้ำ และพื้นที่พิเศษ

Trigger Approval/consent to investigate Initial supporting documents Authority and phase
Ground-mounted project Zoning compatibility and lawful land use Title, cadastral plan, coordinates, layout and intended activity DPT/local authority and relevant land agency; before site commitment
Restricted/state/agricultural-reform/forest land Specific lawful-use permission, if available Land status, proposed use, rights and environmental information Relevant custodian, e.g. ALRO/RFD/DNP; feasibility; consent cannot be assumed
Excavation/filling beyond applicable thresholds Excavation/filling notification Site rights, earthworks/drainage plans, calculations and supervision where prescribed Local authority; before earthworks; 1–3 weeks preliminary allowance
Floating PV Waterbody-use consent and applicable structures/navigation permissions Waterbody jurisdiction, float/mooring layout, electrical routes, safety/access/environmental information Owner/custodian; RID, Marine Department, EGAT or other competent agency as applicable
Road/public-land crossing Excavation, crossing, occupation and reinstatement approval Route/section drawings, method, traffic/reinstatement plan Road owner/local authority; before route works
Third-party land route Consent/easement and associated network assessment Title, surveyed route, installation/maintenance rights Owner/Land Department for registered rights; before construction
Airport vicinity or unusual structures/glare Safeguarding review where triggered Coordinates, elevation, height and glare analysis if requested CAAT/airport operator/relevant aviation authority; design

Confirm earthworks thresholds and territorial application with the local authority. Floating solar, restricted land, aviation and public crossings require individual screening: the applicable legal instrument, form and processing period depend on the site and the authority’s jurisdiction. [R21]

กรณีที่เข้าเงื่อนไข การอนุมัติ/ความยินยอมที่ต้องตรวจสอบ เอกสารประกอบเบื้องต้น หน่วยงานและช่วงเวลา
โครงการติดตั้งบนพื้นดิน ความสอดคล้องกับการใช้ประโยชน์ที่ดินตามผังเมือง และการใช้ที่ดินที่ชอบด้วยกฎหมาย เอกสารสิทธิ์ แผนที่รังวัด พิกัด แผนผัง และกิจกรรมที่ตั้งใจดำเนินการ กรมโยธาธิการและผังเมือง (DPT)/หน่วยงานท้องถิ่น และหน่วยงานที่ดินที่เกี่ยวข้อง ก่อนผูกพันกับพื้นที่
ที่ดินหวงห้าม/ของรัฐ/ปฏิรูปที่ดินเพื่อเกษตรกรรม/ป่าไม้ การอนุญาตให้ใช้ที่ดินโดยชอบด้วยกฎหมายเป็นการเฉพาะ หากมีช่องทางอนุญาต สถานะที่ดิน การใช้ประโยชน์ที่เสนอ สิทธิ และข้อมูลด้านสิ่งแวดล้อม ผู้ดูแลที่ดินที่เกี่ยวข้อง เช่น ส.ป.ก./กรมป่าไม้/กรมอุทยานฯ ช่วงศึกษาความเป็นไปได้ ไม่อาจสันนิษฐานได้ว่าจะได้รับความยินยอม
การขุด/ถมดินเกินเกณฑ์ที่กำหนด การแจ้งการขุด/ถมดิน สิทธิในพื้นที่ แผนงานดิน/ระบายน้ำ รายการคำนวณ และผู้ควบคุมงานตามที่กำหนด หน่วยงานท้องถิ่น ก่อนเริ่มงานดิน ค่าเผื่อเบื้องต้น 1–3 สัปดาห์
PV แบบลอยน้ำ ความยินยอมในการใช้แหล่งน้ำ และการอนุญาตเกี่ยวกับสิ่งปลูกสร้าง/การเดินเรือที่เกี่ยวข้อง เขตอำนาจเหนือแหล่งน้ำ แผนผังทุ่น/การผูกยึด เส้นทางไฟฟ้า ข้อมูลความปลอดภัย/การเข้าถึง/สิ่งแวดล้อม เจ้าของ/ผู้ดูแล กรมชลประทาน กรมเจ้าท่า กฟผ. หรือหน่วยงานอื่นที่มีอำนาจตามที่เกี่ยวข้อง
การข้ามถนน/ที่สาธารณะ การอนุมัติการขุด การข้าม การครอบครอง และการคืนสภาพ แบบเส้นทาง/หน้าตัด วิธีการทำงาน แผนจราจร/การคืนสภาพ เจ้าของถนน/หน่วยงานท้องถิ่น ก่อนเริ่มงานตามแนวเส้นทาง
เส้นทางผ่านที่ดินของบุคคลที่สาม ความยินยอม/ภาระจำยอม และการประเมินโครงข่ายที่เกี่ยวข้อง เอกสารสิทธิ์ แนวเส้นทางที่รังวัดแล้ว สิทธิในการติดตั้ง/บำรุงรักษา เจ้าของ/กรมที่ดินสำหรับสิทธิที่จดทะเบียน ก่อนก่อสร้าง
บริเวณใกล้สนามบินหรือสิ่งปลูกสร้างพิเศษ/แสงสะท้อน การตรวจสอบเพื่อความปลอดภัยทางการบิน ในกรณีที่เข้าเงื่อนไข พิกัด ระดับความสูง ความสูง และการวิเคราะห์แสงสะท้อนหากมีการร้องขอ สำนักงานการบินพลเรือนแห่งประเทศไทย (กพท.)/ผู้ดำเนินการสนามบิน/หน่วยงานการบินที่เกี่ยวข้อง ช่วงออกแบบ

ให้ยืนยันเกณฑ์งานดินและการบังคับใช้ตามพื้นที่กับหน่วยงานท้องถิ่น โซลาร์ลอยน้ำ ที่ดินหวงห้าม การบิน และการข้ามพื้นที่สาธารณะ ต้องพิจารณาเป็นรายกรณี เครื่องมือทางกฎหมาย แบบฟอร์ม และระยะเวลาดำเนินการที่ใช้ขึ้นอยู่กับพื้นที่และเขตอำนาจของหน่วยงาน [R21]

Battery storage, extensions and continuing complianceระบบกักเก็บพลังงานแบตเตอรี่ การขยายระบบ และการปฏิบัติตามกฎระเบียบอย่างต่อเนื่อง

For a PV system with battery storage, record battery energy capacity, PCS power/rating, chemistry, installation location, fire strategy, grid-charging/export modes and protection. Do not assign a blanket solar exemption to storage. Obtain project-specific ERC, utility, building/fire and estate classification as relevant.

Reassess affected permissions when capacity, inverter specification, connection voltage, meter arrangement, export mode, operator or ownership changes. Extensions must be assessed against the existing installation rather than treated automatically as new isolated projects.

Maintain a register of licence expiry, reporting dates, inspection obligations, transfer/change conditions and utility agreements. Renewal dates must come from the actual issued instrument; do not use an assumed universal duration.

สำหรับระบบ PV ที่มีระบบกักเก็บพลังงานแบตเตอรี่ ให้บันทึกความจุพลังงานของแบตเตอรี่ กำลัง/พิกัดของ PCS ชนิดเคมี ตำแหน่งติดตั้ง แนวทางป้องกันอัคคีภัย โหมดการชาร์จจากระบบ/การส่งออก และระบบป้องกัน อย่าถือว่าระบบกักเก็บได้รับยกเว้นแบบเดียวกับโซลาร์โดยอัตโนมัติ ให้ขอการจัดประเภทเฉพาะโครงการจาก กกพ. การไฟฟ้า หน่วยงานอาคาร/ดับเพลิง และนิคมตามที่เกี่ยวข้อง

ประเมินใบอนุญาตที่ได้รับผลกระทบใหม่เมื่อกำลังการผลิต ข้อกำหนดอินเวอร์เตอร์ แรงดันที่เชื่อมต่อ การจัดมิเตอร์ โหมดการส่งออก ผู้ดำเนินการ หรือความเป็นเจ้าของเปลี่ยนแปลง การขยายระบบต้องประเมินเทียบกับระบบที่ติดตั้งอยู่เดิม ไม่ใช่ถือเป็นโครงการใหม่ที่แยกเดี่ยวโดยอัตโนมัติ

จัดทำทะเบียนวันหมดอายุใบอนุญาต วันที่ต้องรายงาน ภาระการตรวจสอบ เงื่อนไขการโอน/เปลี่ยนแปลง และข้อตกลงกับการไฟฟ้า วันต่ออายุต้องมาจากใบอนุญาตที่ออกให้จริง อย่าใช้ระยะเวลาที่สมมติว่าเท่ากันทุกกรณี

Documents, responsibilities and project phasesเอกสาร ความรับผิดชอบ และขั้นตอนของโครงการ

Common project document file

Group Contents
Identity/authorization Company objectives/affidavit, authorized signatories, identification, power of attorney
Site and commercial rights Land/building records, leases, owner/meter-holder consent, PPA/EPC/lease evidence, cable rights
Technical definition DC kWp and AC kW/kVA schedules, existing generators/BESS, SLD, layout, connection point, transformer/protection design
Equipment Specifications, applicable utility acceptance/certification and product-standard evidence
Civil/structural Roof assessment, local loading and wind design, carport/foundation drawings where relevant
Completion As-builts, professional certificates, tests, photographs, approvals and operating conditions

This is a reusable preparation file; it does not mean every document is mandatory for every application.

Allocation of responsibility

Identify the applicant for each permission explicitly. In a PPA project, generator owner, building owner, electricity customer and meter holder may differ. An EPC contractor may prepare and submit documents under authorization without becoming the legal applicant. For an IDN69-supported project, responsibility for maintaining the register, coordinating submissions and checking closeout evidence should be assigned explicitly.

Project gates

Gate Minimum permit-related decision
Feasibility Confirm network, site rights, capacity band, commercial route and fatal site restrictions
Design release Confirm required permits, exemptions, applicants, designs and connection constraints
Construction release Obtain permissions required before the relevant works; record conditions
Commissioning release Complete applicable production/commencement permissions, utility acceptance and test evidence
Handover/operation Deliver approval register, conditions, renewal/reporting calendar and change-control procedure

Permit submission, approval, energization authorization and operational closeout must be separate statuses. A submitted application is not evidence of permission to operate.

แฟ้มเอกสารโครงการทั่วไป

กลุ่ม เนื้อหา
ตัวตน/การมอบอำนาจ วัตถุประสงค์บริษัท/หนังสือรับรอง ผู้มีอำนาจลงนาม เอกสารแสดงตัวตน หนังสือมอบอำนาจ
สิทธิในพื้นที่และสิทธิเชิงพาณิชย์ ทะเบียนที่ดิน/อาคาร สัญญาเช่า หนังสือยินยอมจากเจ้าของ/ผู้ถือมิเตอร์ หลักฐาน PPA/EPC/สัญญาเช่า สิทธิในการเดินสายเคเบิล
ข้อกำหนดทางเทคนิค ตาราง DC kWp และ AC kW/kVA เครื่องกำเนิดไฟฟ้า/BESS ที่มีอยู่เดิม SLD แผนผัง จุดเชื่อมต่อ แบบหม้อแปลง/ระบบป้องกัน
อุปกรณ์ ข้อกำหนดคุณสมบัติ การยอมรับ/การรับรองจากการไฟฟ้าที่เกี่ยวข้อง และหลักฐานมาตรฐานผลิตภัณฑ์
งานโยธา/โครงสร้าง การประเมินหลังคา น้ำหนักบรรทุกเฉพาะจุดและการออกแบบรับลม แบบโรงจอดรถ/ฐานรากในกรณีที่เกี่ยวข้อง
การส่งมอบงาน แบบตามที่ก่อสร้างจริง ใบรับรองผู้ประกอบวิชาชีพ ผลการทดสอบ ภาพถ่าย การอนุมัติ และเงื่อนไขการดำเนินงาน

นี่คือแฟ้มเตรียมการที่นำกลับมาใช้ซ้ำได้ ไม่ได้หมายความว่าทุกเอกสารเป็นข้อบังคับสำหรับทุกคำขอ

การกำหนดความรับผิดชอบ

ระบุผู้ยื่นคำขอสำหรับแต่ละใบอนุญาตให้ชัดเจน ในโครงการ PPA เจ้าของเครื่องกำเนิดไฟฟ้า เจ้าของอาคาร ลูกค้าผู้ใช้ไฟฟ้า และผู้ถือมิเตอร์ อาจเป็นคนละราย ผู้รับเหมา EPC อาจจัดเตรียมและยื่นเอกสารภายใต้หนังสือมอบอำนาจ โดยไม่ได้เป็นผู้ยื่นคำขอตามกฎหมาย สำหรับโครงการที่ IDN69 สนับสนุน ควรกำหนดผู้รับผิดชอบเรื่องการดูแลทะเบียน การประสานการยื่น และการตรวจสอบหลักฐานปิดงานให้ชัดเจน

จุดตัดสินใจของโครงการ

จุดตัดสินใจ การตัดสินใจด้านการขออนุญาตขั้นต่ำ
ศึกษาความเป็นไปได้ ยืนยันโครงข่าย สิทธิในพื้นที่ ช่วงกำลังการผลิต ช่องทางเชิงพาณิชย์ และข้อจำกัดของพื้นที่ที่เป็นอุปสรรคร้ายแรง
อนุมัติให้ออกแบบ ยืนยันใบอนุญาตที่ต้องมี ข้อยกเว้น ผู้ยื่นคำขอ การออกแบบ และข้อจำกัดการเชื่อมต่อ
อนุมัติให้ก่อสร้าง ขอการอนุญาตที่ต้องมีก่อนเริ่มงานที่เกี่ยวข้อง และบันทึกเงื่อนไข
อนุมัติให้ทดสอบเดินเครื่อง ดำเนินการขออนุญาตผลิต/เริ่มดำเนินการที่เกี่ยวข้อง การยอมรับจากการไฟฟ้า และหลักฐานการทดสอบให้เสร็จสิ้น
ส่งมอบ/เดินเครื่อง ส่งมอบทะเบียนการอนุมัติ เงื่อนไข ปฏิทินการต่ออายุ/รายงาน และขั้นตอนควบคุมการเปลี่ยนแปลง

การยื่นขออนุญาต การได้รับอนุมัติ การอนุญาตให้จ่ายไฟ และการปิดงานด้านการดำเนินงาน ต้องแยกเป็นสถานะต่างหากจากกัน คำขอที่ยื่นแล้วไม่ใช่หลักฐานว่าได้รับอนุญาตให้เดินเครื่อง

Timelines and your project compliance registerระยะเวลาและทะเบียนการปฏิบัติตามกฎระเบียบของโครงการ

Allow enough time for approvals

The allowances in the preceding sections are preliminary scheduling estimates, not government service guarantees. Document preparation, corrections, inspections, network reinforcement and third-party consents can extend the overall programme. Several applications may proceed in parallel; their durations should not simply be added together.

For each applicable task, record its dependency: before construction, before equipment installation, before grid-parallel operation or before commercial supply. This helps distinguish permissions needed to begin work from those needed to operate the completed system.

Keep a project-specific compliance register

Field What to record
Requirement Thai/English name and type: licence, notification, utility approval or consent
Applicability Required; exempt with conditions; not applicable; or authority confirmation pending
Reason and evidence Capacity/site/commercial trigger, legal basis and source revision
Responsibility Legal applicant, document preparer and submission coordinator
Programme Prerequisites, relevant project phase and target submission/decision dates
Approval record Submission receipt, decision, approved drawings and attached conditions
Continuing duties Expiry, renewal, reporting, inspections and change/transfer requirements

A submission receipt demonstrates that documents were submitted. It does not, by itself, demonstrate approval or authorization to operate.

เผื่อเวลาสำหรับการอนุมัติให้เพียงพอ

ค่าเผื่อเวลาในหัวข้อก่อนหน้าเป็นประมาณการกำหนดการเบื้องต้น ไม่ใช่การรับประกันการให้บริการของรัฐ การเตรียมเอกสาร การแก้ไข การตรวจสอบ การเสริมโครงข่าย และความยินยอมจากบุคคลที่สาม อาจทำให้ระยะเวลาโครงการโดยรวมยาวขึ้น คำขอหลายรายการดำเนินการขนานกันได้ จึงไม่ควรนำระยะเวลามารวมกันตรง ๆ

สำหรับแต่ละงานที่เกี่ยวข้อง ให้บันทึกความสัมพันธ์เชิงลำดับ เช่น ก่อนก่อสร้าง ก่อนติดตั้งอุปกรณ์ ก่อนเดินเครื่องขนานระบบ หรือก่อนจ่ายไฟเชิงพาณิชย์ วิธีนี้ช่วยแยกใบอนุญาตที่ต้องมีเพื่อเริ่มงานออกจากที่ต้องมีเพื่อเดินเครื่องระบบที่สร้างเสร็จแล้ว

จัดทำทะเบียนการปฏิบัติตามข้อกำหนดเฉพาะโครงการ

หัวข้อ สิ่งที่ต้องบันทึก
ข้อกำหนด ชื่อภาษาไทย/อังกฤษ และประเภท: ใบอนุญาต การแจ้ง การอนุมัติจากการไฟฟ้า หรือความยินยอม
การนำไปใช้ ต้องมี ยกเว้นแต่มีเงื่อนไข ไม่เกี่ยวข้อง หรือรอการยืนยันจากหน่วยงาน
เหตุผลและหลักฐาน ปัจจัยที่ทำให้เข้าเงื่อนไขด้านกำลังการผลิต/พื้นที่/เชิงพาณิชย์ ฐานทางกฎหมาย และฉบับของแหล่งอ้างอิง
ผู้รับผิดชอบ ผู้ยื่นคำขอตามกฎหมาย ผู้จัดเตรียมเอกสาร และผู้ประสานงานการยื่น
กำหนดการ เงื่อนไขเบื้องต้น ช่วงของโครงการที่เกี่ยวข้อง และวันที่เป้าหมายสำหรับการยื่น/การตัดสิน
บันทึกการอนุมัติ ใบรับเรื่อง ผลการตัดสิน แบบที่ได้รับอนุมัติ และเงื่อนไขที่แนบมา
ภาระต่อเนื่อง วันหมดอายุ การต่ออายุ การรายงาน การตรวจสอบ และข้อกำหนดการเปลี่ยนแปลง/โอน

ใบรับเรื่องแสดงเพียงว่ามีการยื่นเอกสารแล้ว ไม่ได้แสดงด้วยตัวเองว่าได้รับอนุมัติหรือได้รับอนุญาตให้เดินเครื่อง

Frequently asked questionsคำถามที่พบบ่อย

Is a project below 200 kVA permit-free?

No. It generally avoids พค.2 and the full generation-licence route, but the applicable exemption notification and grid-connection process remain. Building, land, estate and commercial arrangements can introduce other requirements. [R1–R3]

Should I use panel kWp or inverter kVA to choose the capacity band?

Use the applicable generating-source rating in kVA for the energy thresholds described here. Record panel DC kWp separately. Check aggregation where an existing system, multiple buildings, other generators or battery storage are involved. [R3]

Does zero export remove the need for utility approval?

No. A system operating in parallel with the grid still needs the applicable connection assessment and authorization. Zero-export protection is part of the operating arrangement. [R9–R12]

Does the rooftop building exemption also cover a new carport?

Not automatically. A new carport or canopy is a construction activity that must be assessed separately. The exemption for qualifying panels on a roof does not by itself authorize construction of the supporting building. [R13]

Does rooftop solar above 1 MW automatically need ร.ง.4?

No. The amended rooftop factory classification excludes rooftop solar at all capacities. Generation licensing, พค.2, utility requirements and other site obligations still require their own assessment. [R3, R14]

Can I sell surplus electricity once the system is connected?

Connection permission alone does not create an entitlement to paid export. Confirm eligibility under the applicable procurement scheme and complete the necessary agreement and operating conditions. [R9–R12]

Are all requirements the same for an onsite PPA and an owner-funded installation?

No. An onsite PPA may separate generator ownership, building ownership and meter-holder identity. Confirm the legal applicant, property consents, commercial arrangement and applicable sale/distribution classification. [R3, R4]

What should be checked when the system is expanded?

Reassess aggregate capacity and the approved technical/commercial arrangement. Review affected licences, notifications, utility agreements, drawings and site permissions before making the regulated change.

Can a factory still get BOI tax exemption for rooftop solar?

Not through the own-use solar-installation measure for applications filed from 1 July 2025, according to the sources reviewed. A project with an earlier filing, a power-producer route or battery storage may differ. Treat any BOI benefit as unconfirmed until BOI says so in writing, and model returns without it. [R24, R26]

โครงการที่ต่ำกว่า 200 kVA ไม่ต้องขออนุญาตใช่หรือไม่?

ไม่ใช่ โดยทั่วไปไม่ต้องขอ พค.2 และไม่ต้องผ่านช่องทางใบอนุญาตผลิตไฟฟ้าเต็มรูปแบบ แต่ยังต้องแจ้งเพื่อรับยกเว้นและผ่านกระบวนการเชื่อมต่อระบบไฟฟ้าที่เกี่ยวข้อง ส่วนอาคาร ที่ดิน นิคม และรูปแบบเชิงพาณิชย์ อาจทำให้มีข้อกำหนดอื่นเพิ่มเติม [R1–R3]

ควรใช้ kWp ของแผง หรือ kVA ของอินเวอร์เตอร์ ในการเลือกช่วงกำลังการผลิต?

ให้ใช้พิกัดของแหล่งผลิตไฟฟ้าที่เกี่ยวข้องในหน่วย kVA สำหรับเกณฑ์ด้านพลังงานที่อธิบายไว้ในที่นี้ และบันทึก DC kWp ของแผงแยกต่างหาก ให้ตรวจสอบการรวมกำลังการผลิตในกรณีที่มีระบบเดิม อาคารหลายหลัง เครื่องกำเนิดไฟฟ้าอื่น หรือระบบกักเก็บพลังงานแบตเตอรี่ [R3]

ระบบไม่ส่งออกไฟฟ้า (zero export) ทำให้ไม่ต้องขออนุมัติจากการไฟฟ้าใช่หรือไม่?

ไม่ใช่ ระบบที่เดินเครื่องขนานกับระบบไฟฟ้ายังต้องผ่านการประเมินและอนุญาตการเชื่อมต่อที่เกี่ยวข้อง การป้องกันการส่งออกเป็นส่วนหนึ่งของรูปแบบการเดินเครื่อง [R9–R12]

ข้อยกเว้นด้านอาคารสำหรับหลังคาครอบคลุมโรงจอดรถใหม่ด้วยหรือไม่?

ไม่โดยอัตโนมัติ โรงจอดรถหรือหลังคาคลุมใหม่เป็นกิจกรรมก่อสร้างที่ต้องประเมินแยกต่างหาก ข้อยกเว้นสำหรับแผงที่เข้าเกณฑ์บนหลังคาไม่ได้อนุญาตให้ก่อสร้างอาคารที่รองรับแผงด้วยตัวเอง [R13]

โซลาร์บนหลังคาเกิน 1 MW ต้องมี ร.ง.4 โดยอัตโนมัติหรือไม่?

ไม่ การจัดประเภทโรงงานบนหลังคาที่แก้ไขแล้วไม่นับโซลาร์บนหลังคาทุกขนาดกำลัง แต่ใบอนุญาตผลิตไฟฟ้า พค.2 ข้อกำหนดของการไฟฟ้า และภาระอื่นของพื้นที่ ยังต้องประเมินแยกต่างหาก [R3, R14]

เมื่อเชื่อมต่อระบบแล้ว ขายไฟฟ้าส่วนเกินได้หรือไม่?

การอนุญาตให้เชื่อมต่อเพียงอย่างเดียวไม่ได้ทำให้มีสิทธิส่งออกไฟฟ้าเพื่อรับค่าตอบแทน ให้ยืนยันคุณสมบัติตามโครงการรับซื้อไฟฟ้าที่เกี่ยวข้อง และดำเนินการเรื่องข้อตกลงและเงื่อนไขการเดินเครื่องที่จำเป็นให้ครบถ้วน [R9–R12]

ข้อกำหนดทั้งหมดเหมือนกันระหว่าง PPA ในพื้นที่กับการลงทุนติดตั้งเองหรือไม่?

ไม่เหมือนกัน PPA ในพื้นที่อาจแยกความเป็นเจ้าของเครื่องกำเนิดไฟฟ้า ความเป็นเจ้าของอาคาร และผู้ถือมิเตอร์ออกจากกัน ให้ยืนยันผู้ยื่นคำขอตามกฎหมาย ความยินยอมด้านทรัพย์สิน รูปแบบเชิงพาณิชย์ และการจัดประเภทการขาย/จำหน่ายที่เกี่ยวข้อง [R3, R4]

เมื่อขยายระบบ ควรตรวจสอบอะไรบ้าง?

ประเมินกำลังการผลิตรวมและรูปแบบทางเทคนิค/เชิงพาณิชย์ที่ได้รับอนุมัติใหม่ ตรวจสอบใบอนุญาต การแจ้ง ข้อตกลงกับการไฟฟ้า แบบ และการอนุญาตเกี่ยวกับพื้นที่ที่ได้รับผลกระทบ ก่อนดำเนินการเปลี่ยนแปลงที่อยู่ในการควบคุม

โรงงานยังขอรับยกเว้นภาษีจาก BOI สำหรับโซลาร์บนหลังคาได้หรือไม่?

ตามแหล่งข้อมูลที่ตรวจสอบ ไม่สามารถขอผ่านมาตรการติดตั้งโซลาร์เพื่อใช้เองสำหรับคำขอที่ยื่นตั้งแต่ 1 กรกฎาคม 2568 (1 July 2025) เป็นต้นไป โครงการที่ยื่นก่อนหน้านั้น ช่องทางผู้ผลิตไฟฟ้า หรือที่มีระบบกักเก็บพลังงานแบตเตอรี่ อาจแตกต่างออกไป ให้ถือว่าสิทธิประโยชน์ใด ๆ จาก BOI ยังไม่ยืนยัน จนกว่า BOI จะยืนยันเป็นลายลักษณ์อักษร และให้คำนวณผลตอบแทนโดยไม่รวมสิทธิประโยชน์นั้น [R24, R26]

BOI investment promotion (optional incentive)การส่งเสริมการลงทุนจาก BOI (สิทธิประโยชน์ที่เลือกขอได้)

Pending verification

BOI (the Board of Investment) promotion is an optional tax and duty incentive. It is not a permit to build or operate. A BOI certificate does not replace any ERC, utility, building, factory or estate approval described in sections 2 to 9, and an exemption or benefit under BOI does not remove them. This section exists because a BOI benefit is often assumed in a solar financial case when it may not be available.

Planning rule: do not assume a BOI benefit for a new own-use or onsite-PPA rooftop project. Model returns without BOI first, and add a BOI benefit only after BOI confirms in writing which route applies and on what terms. [R23, R24]

Which BOI route, if any

BOI route Typically for Status in this research Reported terms
Solar-installation measure for existing businesses (own-use rooftop or ground PV at a factory) Existing factories adding PV for their own use Closed to new applications filed from 1 July 2025 (BOI Announcement 3/2568, issued 5 June 2025). Applications filed up to 30 June 2025 follow the rules in force when filed. Former terms: machinery import-duty exemption and a 3-year corporate income tax (CIT) exemption, capped at 50% of investment capital; minimum investment THB 1 million excluding land and working capital. The investment counted per MW was capped, and the cap figure changed between announcements (THB 12, 30 and 40 million per MW all appear in the sources). [R24, R25, R26]
Renewable electricity generation for sale (BOI activity list) Power producers selling electricity under an available utility or procurement arrangement Listed in the BOI activity list; current availability not verified. This is a power-producer route, not an own-use route. BOI 2020 activity list: production of electricity from renewable energy such as solar, group A2, 8-year CIT exemption, subject to approval by relevant government agencies. A vendor summary adds a minimum of 200 kW per distribution point and a cap of 100% of investment; neither was confirmed in a BOI text. [R23, R26]
Battery energy storage with a solar installation Projects adding BESS Reported as still considered case by case; confirm with BOI. Counted investment for the CIT exemption capped at THB 12 million per MW of capacity (secondary summary of Announcement 3/2568). [R24, R26]
SME measure (Announcement 5/2568) Small and medium enterprises Unconfirmed whether rooftop solar qualifies. Not relied on in this guide. [R26]

The status and terms above come from the BOI 2020 activity list and from law-firm and vendor summaries of BOI announcements. The BOI announcements themselves were not retrieved, so every figure here is a lead to confirm against the current BOI text, not a basis for a financial commitment. [R23, R24, R25, R26]

What to confirm with BOI before relying on a benefit

  • Which announcement applies, and the date your application was or will be filed. Filing date decided eligibility under the closed measure.
  • Whether your activity is own-use, sale of electricity, or both, and whether any minimum capacity per distribution point applies.
  • Whether the project already has a BOI certificate, its conditions, expiry, and its completion deadline (a vendor summary reports completion within 3 years of the certificate date).
  • Which equipment and installation costs count toward the benefit (the earlier measure listed PV modules, inverters, transformers, distribution systems, weather stations, panel-cleaning systems, BESS and BESS inverters, and mounting-structure installation costs) and the cap per MW.
  • Whether the benefit must be applied for before equipment is purchased or installed. Do not assume a benefit can be claimed after the work.

A separate Royal Decree No. 805 deduction for certified energy-efficient equipment, and a personal income tax deduction for residential rooftop solar, are reported in a secondary source. They are not BOI measures, and that source does not establish that commercial PV equipment qualifies. Screen them with a tax adviser; they are not used in this guide. [R27]

How this appears in the IDN69 financial tool

The solar explorer has a BOI switch that models an income-tax exemption. Treat it as a scenario for a project that already holds an eligible BOI certificate or whose route BOI has confirmed, not as a default for new own-use projects.

การส่งเสริมการลงทุนจาก BOI (สำนักงานคณะกรรมการส่งเสริมการลงทุน) เป็นสิทธิประโยชน์ทางภาษีและอากรที่เลือกขอได้ ไม่ใช่ใบอนุญาตก่อสร้างหรือเดินเครื่อง บัตรส่งเสริมการลงทุนของ BOI ไม่ได้ใช้แทนการอนุมัติของ กกพ. การไฟฟ้า อาคาร โรงงาน หรือนิคมที่อธิบายไว้ในหัวข้อ 2 ถึง 9 และการยกเว้นหรือสิทธิประโยชน์ของ BOI ไม่ได้ยกเว้นข้อกำหนดเหล่านั้น หัวข้อนี้มีขึ้นเพราะมักมีการสมมติว่าจะได้สิทธิประโยชน์จาก BOI ในการวิเคราะห์ทางการเงินของโซลาร์ ทั้งที่อาจไม่มีสิทธินั้น

หลักการวางแผน: อย่าสมมติว่าจะได้สิทธิประโยชน์จาก BOI สำหรับโครงการโซลาร์บนหลังคาใหม่ที่ใช้เองหรือทำ PPA ในพื้นที่ ให้คำนวณผลตอบแทนโดยไม่รวม BOI ก่อน และเพิ่มสิทธิประโยชน์จาก BOI ก็ต่อเมื่อ BOI ยืนยันเป็นลายลักษณ์อักษรแล้วว่าใช้ช่องทางใดและเงื่อนไขอย่างไร [R23, R24]

ช่องทาง BOI ใด (ถ้ามี)

ช่องทาง BOI โดยทั่วไปใช้กับ สถานะในการศึกษานี้ เงื่อนไขที่มีรายงาน
มาตรการติดตั้งโซลาร์สำหรับกิจการที่ดำเนินการอยู่เดิม (PV บนหลังคาหรือบนพื้นดินที่โรงงานเพื่อใช้เอง) โรงงานเดิมที่เพิ่มระบบ PV เพื่อใช้เอง ปิดรับคำขอใหม่ที่ยื่นตั้งแต่ 1 กรกฎาคม 2568 (1 July 2025) (ประกาศ BOI ที่ 3/2568 ออกเมื่อ 5 มิถุนายน 2568) คำขอที่ยื่นภายใน 30 มิถุนายน 2568 ใช้กฎที่บังคับใช้ ณ วันที่ยื่น เงื่อนไขเดิม: ยกเว้นอากรขาเข้าเครื่องจักร และยกเว้นภาษีเงินได้นิติบุคคล (CIT) 3 ปี โดยจำกัดที่ 50% ของเงินลงทุน เงินลงทุนขั้นต่ำ 1 ล้านบาท ไม่รวมที่ดินและทุนหมุนเวียน เงินลงทุนที่นับต่อ MW มีเพดาน และตัวเลขเพดานเปลี่ยนไปตามประกาศแต่ละฉบับ (พบทั้ง 12, 30 และ 40 ล้านบาทต่อ MW ในแหล่งข้อมูล) [R24, R25, R26]
การผลิตไฟฟ้าจากพลังงานหมุนเวียนเพื่อขาย (บัญชีกิจการของ BOI) ผู้ผลิตไฟฟ้าที่ขายไฟฟ้าภายใต้การรับซื้อของการไฟฟ้าหรือรูปแบบการรับซื้อที่เปิดอยู่ อยู่ในบัญชีกิจการของ BOI ยังไม่ได้ตรวจสอบว่าเปิดให้ขอได้หรือไม่ในปัจจุบัน นี่เป็นช่องทางของผู้ผลิตไฟฟ้า ไม่ใช่ช่องทางสำหรับใช้เอง บัญชีกิจการ BOI ปี 2563 (2020): การผลิตไฟฟ้าจากพลังงานหมุนเวียน เช่น โซลาร์ กลุ่ม A2 ยกเว้น CIT 8 ปี ภายใต้การอนุมัติของหน่วยงานรัฐที่เกี่ยวข้อง สรุปจากผู้จำหน่ายระบุเพิ่มเติมว่ามีขั้นต่ำ 200 kW ต่อจุดจำหน่าย และเพดาน 100% ของเงินลงทุน ซึ่งทั้งสองข้อยังไม่ได้รับการยืนยันจากเอกสารของ BOI [R23, R26]
ระบบกักเก็บพลังงานแบตเตอรี่ร่วมกับโซลาร์ โครงการที่เพิ่ม BESS มีรายงานว่ายังพิจารณาเป็นรายกรณี ควรยืนยันกับ BOI เงินลงทุนที่นับเพื่อยกเว้น CIT มีเพดาน 12 ล้านบาทต่อ MW ของกำลังการผลิต (สรุปจากแหล่งข้อมูลรองของประกาศ 3/2568) [R24, R26]
มาตรการสำหรับ SME (ประกาศ 5/2568) วิสาหกิจขนาดกลางและขนาดย่อม ยังไม่ยืนยันว่าโซลาร์บนหลังคาเข้าเกณฑ์หรือไม่ คู่มือนี้ไม่ได้ใช้เป็นฐานอ้างอิง [R26]

สถานะและเงื่อนไขข้างต้นมาจากบัญชีกิจการของ BOI ปี 2563 และจากบทสรุปของสำนักงานกฎหมายและผู้จำหน่ายเกี่ยวกับประกาศของ BOI ยังไม่ได้ตรวจสอบตัวประกาศของ BOI เอง ดังนั้นตัวเลขทุกตัวในที่นี้เป็นเพียงแนวทางที่ต้องยืนยันกับข้อความฉบับปัจจุบันของ BOI ไม่ใช่ฐานสำหรับการผูกพันทางการเงิน [R23, R24, R25, R26]

สิ่งที่ควรยืนยันกับ BOI ก่อนพึ่งพาสิทธิประโยชน์

  • ประกาศฉบับใดที่ใช้บังคับ และวันที่ที่คุณยื่นหรือจะยื่นคำขอ วันที่ยื่นเป็นตัวกำหนดสิทธิภายใต้มาตรการที่ปิดรับแล้ว
  • กิจกรรมของคุณเป็นการใช้เอง การขายไฟฟ้า หรือทั้งสองอย่าง และมีเกณฑ์กำลังการผลิตขั้นต่ำต่อจุดจำหน่ายหรือไม่
  • โครงการมีบัตรส่งเสริมการลงทุนของ BOI อยู่แล้วหรือไม่ เงื่อนไข วันหมดอายุ และกำหนดเวลาแล้วเสร็จ (สรุปจากผู้จำหน่ายระบุว่าต้องแล้วเสร็จภายใน 3 ปีนับจากวันที่ออกบัตร)
  • ค่าอุปกรณ์และค่าติดตั้งใดบ้างที่นับรวมเป็นสิทธิประโยชน์ (มาตรการเดิมระบุแผง PV อินเวอร์เตอร์ หม้อแปลง ระบบจำหน่าย สถานีตรวจวัดอากาศ ระบบทำความสะอาดแผง BESS และอินเวอร์เตอร์ BESS และค่าติดตั้งโครงสร้างรองรับ) และเพดานต่อ MW
  • ต้องขอรับสิทธิประโยชน์ก่อนซื้อหรือติดตั้งอุปกรณ์หรือไม่ อย่าสมมติว่าขอรับสิทธิประโยชน์ได้หลังจากทำงานเสร็จแล้ว

การหักรายจ่ายตามพระราชกฤษฎีกาฉบับที่ 805 สำหรับอุปกรณ์ประหยัดพลังงานที่ได้รับการรับรอง และการหักลดหย่อนภาษีเงินได้บุคคลธรรมดาสำหรับโซลาร์บนหลังคาที่อยู่อาศัย มีรายงานในแหล่งข้อมูลรอง มาตรการเหล่านี้ไม่ใช่มาตรการของ BOI และแหล่งข้อมูลดังกล่าวไม่ได้ยืนยันว่าอุปกรณ์ PV เชิงพาณิชย์เข้าเกณฑ์ ควรตรวจสอบกับที่ปรึกษาด้านภาษี คู่มือนี้ไม่ได้ใช้มาตรการเหล่านี้ [R27]

เรื่องนี้ปรากฏในเครื่องมือการเงินของ IDN69 อย่างไร

เครื่องมือประเมินมีสวิตช์ BOI ที่จำลองการยกเว้นภาษีเงินได้ ให้ถือว่าเป็นสถานการณ์สมมติสำหรับโครงการที่ถือบัตรส่งเสริมการลงทุนของ BOI ที่มีสิทธิอยู่แล้ว หรือที่ BOI ยืนยันช่องทางแล้ว ไม่ใช่ค่าเริ่มต้นสำหรับโครงการใหม่ที่ใช้เอง

References and official resourcesเอกสารอ้างอิงและแหล่งข้อมูลทางการ

Pending verification

The resources below support the research baseline dated 7 November 2026. Use later effective amendments and current authority checklists where they supersede an older reference. Source notes identify historic guides, government summaries and attachments needing further confirmation.

Regulatory updates: Draft legislation and Cabinet approval of a draft do not by themselves establish an effective exemption. The proposed solar-promotion bill referenced at R22 is included for context; its draft provisions have not been used to remove requirements in this guide. BOI sources R23 to R27 are a 2020 BOI list plus secondary summaries; the BOI announcements themselves are to be obtained.

Items requiring project-stage confirmation: Complete operative 2025 notification attachments; any newer พค.2 checklist/workflow; current utility equipment/grid-code rules; site-specific permissions; subsequent effective solar legislation; and the current BOI announcement text and terms (section 13).

แหล่งข้อมูลด้านล่างสนับสนุนฐานการวิจัยลงวันที่ 7 พฤศจิกายน 2569 (7 November 2026) ให้ใช้ฉบับแก้ไขที่มีผลบังคับใช้ภายหลังและรายการตรวจของหน่วยงานฉบับปัจจุบัน ในกรณีที่ใช้แทนเอกสารอ้างอิงที่เก่ากว่า หมายเหตุแหล่งที่มาระบุคู่มือฉบับเก่า บทสรุปของหน่วยงานรัฐ และเอกสารแนบที่ต้องยืนยันเพิ่มเติม

ข้อมูลการเปลี่ยนแปลงทางกฎระเบียบ: ร่างกฎหมายและการที่คณะรัฐมนตรีเห็นชอบร่าง ไม่ได้ทำให้ข้อยกเว้นมีผลบังคับใช้ด้วยตัวเอง ร่างพระราชบัญญัติส่งเสริมโซลาร์ที่อ้างถึงใน R22 รวมไว้เพื่อให้เห็นบริบท โดยไม่ได้นำบทบัญญัติร่างมาใช้ยกเลิกข้อกำหนดใด ๆ ในคู่มือนี้ แหล่งข้อมูล BOI ที่ R23 ถึง R27 เป็นบัญชีกิจการของ BOI ปี 2563 และบทสรุปจากแหล่งรอง ส่วนตัวประกาศของ BOI ยังต้องจัดหามา

รายการที่ต้องยืนยันในช่วงของโครงการ: เอกสารแนบประกาศปี 2568 ฉบับที่มีผลบังคับใช้ครบถ้วน รายการตรวจ/ขั้นตอน พค.2 ฉบับใหม่กว่า (ถ้ามี) ข้อกำหนดอุปกรณ์/Grid Code ของการไฟฟ้าฉบับปัจจุบัน การอนุญาตเฉพาะพื้นที่ กฎหมายโซลาร์ที่มีผลบังคับใช้ภายหลัง และข้อความและเงื่อนไขของประกาศ BOI ฉบับปัจจุบัน (หัวข้อ 13)

RefSourceUse and evidence qualification
R1 ERC: 2025 exempt-electricity-business notification announcement 2025 procedure; landing-page record verified; full attachments require final pre-publication checking
R2 ERC: updated exemption-process infographic Below-200 and 200-to-below-1,000 kVA routes; detailed diagrams should be checked before selecting the submission sequence
R3 ERC: solar project permitting guide, October 2023 Capacity basis, source aggregation and agency interfaces; historic factory/building rules superseded where subsequently amended
R4 ERC: application forms and licensing manuals Generation, distribution and sale licensing; current application route
R5 ERC: controlled-energy production licensing พค.1/พค.2, DEDE inspection framework and 2025 application announcement
R6 ERC: พค.2 checklist, marked May 2026 Directly retrieved checklist; recheck for later revision
R7 ERC: commencement-of-electricity-operations resources Solar checklist and rooftop self-declaration procedure
R8 Government service guide: ERC licensing and commencement notice General thresholds/advance-notice context; older service guide, verify current procedure
R9 MEA: MyEnergy Self-use versus eligible utility-sale pathways
R10 MEA: C&I/self-use project checklist Technical documents and engineer/measurement requirements; dynamic checklist must be rechecked
R11 PEA: producer connection services PEA application entry point
R12 PEA PPIM: DG-SELF Self-use connection route, guides and equipment references
R13 Ministerial Regulation No. 72, B.E. 2568 — Gazette copy hosted by Ang Sila Municipality Page links the regulation; Gazette publication 19 November 2025; rooftop non-alteration provision
R14 Thailand government portal: rooftop factory-rule amendment Government explanation of Ministerial Regulation No. 3, B.E. 2567; obtain operative Gazette text when confirming a project’s legal basis
R15 DIW: factory electrical safety legislation Host-factory safety obligations separate from rooftop factory classification
R16 IEAT: service procedures Land-use/business permission, expansion, amendment and commencement
R17 IEAT: application forms Relevant estate application categories
R18 ERC: CoP report/checklist framework, Version 1.0/2567 Environmental documentation framework
R19 Royal Gazette: ERC CoP amendment, B.E. 2567 Legal reference identified through the Department of Science Service official catalogue; operative annex selection requires checking
R20 ONEP: environmental assessment FAQs Host-development and sensitive-location screening context
R21 Local-authority guidance: excavation and filling Practical statutory/local-threshold screening; confirm with actual site authority
R22 Government PRD: Cabinet approval in principle of the draft solar-promotion bill, July 2025 Policy watch only; draft provisions not treated as effective exemptions
R23 BOI: A Guide to the Board of Investment 2020, activity list (section 7) BOI document, dated 2020. Lists renewable electricity generation (group A2, 8 years). Re-check the activity number, group and conditions against the current BOI list.
R24 B Global Law: BOI Announcement No. 3/2568 summary Secondary source. Reports issue date 5 June 2025, effect from 1 July 2025, and removal of promotion for standalone solar installations under the measure. Obtain the BOI announcement text.
R25 Law Plus: BOI Announcement No. 2/2568 summary Secondary source. Reports issue date 9 April 2025, 3-year CIT exemption capped at 50% of investment and per-MW investment caps. Earlier terms, superseded for new solar-installation applications by Announcement 3/2568 according to R24.
R26 CapSolar: BOI solar incentives 2026 Vendor blog (an EPC/PPA seller). Used only for status context and for items marked unverified. Defers to the official BOI text.
R27 Lex Bangkok: Thailand green energy tax incentives Secondary source, page dated 2026. Mentions non-BOI deductions. Does not describe BOI solar eligibility.

Glossaryอภิธานศัพท์

TermMeaning
ERC / กกพ.Energy Regulatory Commission / Office of the ERC as applicableคณะกรรมการกำกับกิจการพลังงาน / สำนักงานคณะกรรมการกำกับกิจการพลังงาน แล้วแต่กรณี
DEDE / พพ.Department of Alternative Energy Development and Efficiencyกรมพัฒนาพลังงานทดแทนและอนุรักษ์พลังงาน
MEA / กฟน.Metropolitan Electricity Authorityการไฟฟ้านครหลวง
PEA / กฟภ.Provincial Electricity Authorityการไฟฟ้าส่วนภูมิภาค
EGAT / กฟผ.Electricity Generating Authority of Thailandการไฟฟ้าฝ่ายผลิตแห่งประเทศไทย
DIW / กรอ.Department of Industrial Worksกรมโรงงานอุตสาหกรรม
IEAT / กนอ.Industrial Estate Authority of Thailandการนิคมอุตสาหกรรมแห่งประเทศไทย
DPTDepartment of Public Works and Town & Country Planningกรมโยธาธิการและผังเมือง
ONEP / สผ.Office of Natural Resources and Environmental Policy and Planningสำนักงานนโยบายและแผนทรัพยากรธรรมชาติและสิ่งแวดล้อม
CoPCode of Practiceประมวลหลักปฏิบัติ (Code of Practice)
EIA / IEEEnvironmental Impact Assessment / Initial Environmental Examinationการประเมินผลกระทบสิ่งแวดล้อม / การตรวจสอบสิ่งแวดล้อมเบื้องต้น
SLDSingle-line diagramแผนผังเส้นเดี่ยว (Single-line diagram)
BESS / PCSBattery energy storage system / power conversion systemระบบกักเก็บพลังงานแบตเตอรี่ / ระบบแปลงกำลังไฟฟ้า
CODCommercial operation dateวันเริ่มดำเนินการเชิงพาณิชย์

Published as an IDN69 knowledge resource. Project-specific applicability remains subject to the competent authority’s requirements and the conditions of the actual approvals.